Project Management Professional (PMP) — Question 1076
A company's leadership team has decided to invest in a new product using an agile approach. The commercial and product teams have started the planning activity for this new venture.
Which three key factors does the project manager need in order to deliver this product? (Choose three.)
Answer options
- A. Product roadmap
- B. Schedule performance indexes (SPIs)
- C. Product vision
- D. Key performance indicators (KPIs)
- E. High-level product backlog
Correct answer: A, C, E
Explanation
The correct answer includes the Product roadmap, Product vision, and High-level product backlog, as these are crucial for guiding the development process in an agile environment. Schedule performance indexes (SPIs) and Key performance indicators (KPIs) are important for measuring performance but are not foundational elements needed for product delivery in this context.