Project Management Professional (PMP) — Question 106
In a daily standup meeting, a developer indicates that a backlog item will not be delivered because they need to take an unexpected leave for the next couple of days. The backlog item is a prerequisite for a feature expected by users in the next sprint review.
What should the project lead do?
Answer options
- A. Work with the product owner to change the priorities in the sprint backlog.
- B. Work with the product owner to inform the users that the feature is delayed.
- C. Ask the development manager to provide a replacement for a couple of days.
- D. Ask the developer to postpone the leave until the backlog item is delivered.
Correct answer: A
Explanation
The correct answer is A because adjusting the priorities in the sprint backlog allows the team to focus on the most critical tasks, ensuring that user expectations are met. Options B and C do not address the immediate need to prioritize the backlog effectively, while option D is not a feasible or ethical request to make of the developer.