Project Management Professional (PMP) — Question 1035
During a meeting with project stakeholders, a stakeholder who is known for causing problems, questions the project manager’s authority to implement new processes for functional managers. What should the project manager do?
Answer options
- A. Refer to the change management plan and review the documented process changes.
- B. Meet with the stakeholder individually.
- C. Refer the stakeholder to the approved project charter.
- D. Explain that the potential risks will be addressed in the risk management plan.
Correct answer: C
Explanation
The correct answer is C because the project charter outlines the authority and scope of the project, providing a solid basis for the project manager's decisions. The other options do not directly reference the foundational document that legitimizes the project manager’s authority, which is essential in this context.