Project Management Professional (PMP) — Question 1025
A project stakeholder has expressed concern that the established success criteria for the project are not being met. What should the project manager do next?
Answer options
- A. Document the agreed-upon ownership of benefits realization.
- B. Review the established project benefits tracking metrics.
- C. Create a project benefits management plan.
- D. Update the project business case document.
Correct answer: B
Explanation
The correct answer is B because reviewing the established project benefits tracking metrics allows the project manager to assess whether the project is on track to meet its success criteria. Options A, C, and D are related to managing benefits but do not directly address the immediate concern of whether the success criteria are being met.