Project Management Professional (PMP) — Question 1018
Within a project, senior management is requesting project information so they can analyze the data to make project decisions. What information should the project manager provide so that senior management can get a broader view of the project?
Answer options
- A. Higher-level activities completed
- B. Milestones status report
- C. Risk register information
- D. Resource breakdown structure (RBS)
Correct answer: B
Explanation
The correct answer is B, as a milestones status report provides a clear overview of significant achievements and progress within the project. Options A, C, and D, while informative, do not offer the same level of high-level insight into the overall project status that a milestones status report does.