A project team member is having difficulty delivering assigned tasks for a project that is at risk of being delayed. The main issue is that the team member does not understand a new system that was recently implemented.
What should the project manager do?

Answer options

Correct answer: D

Explanation

The correct answer is D because providing support from an experienced resource can help the team member understand the new system and complete their tasks more effectively. Option A is insufficient as it places the burden solely on the team member without immediate assistance. Option B does not address the root cause of the problem, and option C may escalate the issue unnecessarily without providing a solution.