PMI Scheduling Professional (PMI-SP) — Question 9
You are working with your project team to control the project schedule. You will need five inputs to this process throughout your project. Which one of the following is an output of the project schedule control, and NOT an input?
Answer options
- A. Work performance information
- B. Project schedule
- C. Project management plan
- D. Work performance measurements
Correct answer: D
Explanation
The correct answer, D, 'Work performance measurements', is an output derived from analyzing the project schedule control process, reflecting the performance of the project against the baseline. In contrast, options A, B, and C are all inputs needed to effectively manage the project schedule, as they provide essential information and frameworks necessary for control activities.