PMI Scheduling Professional (PMI-SP) — Question 49

You work as the project manager for BlueWell Inc. You are reviewing and regulating the progress to meet the performance objectives defined in the project management plan. Mark, a trainee, has a doubt related to the inputs of monitor and control project work. Which of the following is the input to monitor and control project work?

Answer options

Correct answer: C

Explanation

The correct answer is C, as the performance report provides essential data on the project's progress and performance metrics, which are crucial for monitoring and controlling efforts. Options A and D are outputs rather than inputs, and while B (Expert judgment) can be used in the process, it is not a direct input like the performance report.