PMI Scheduling Professional (PMI-SP) — Question 33

Gina is the project manager for her organization and she is working with her project team to define the project activities. In this project, the stakeholders are sensitive to the project completion date, so Gina is stressing to her project team members that while they need to provide and account for all of the project activities, they should focus on one work package in the WBS at a time. In order to start the decomposition of the project work packages into activities, Gina will need all of the following except for which one?

Answer options

Correct answer: C

Explanation

The correct answer is C, as the WBS itself is what Gina is trying to decompose into activities. The scope baseline, organizational process assets, and enterprise environmental factors are all necessary inputs for the decomposition process, whereas the WBS is the output that needs to be broken down.