PMI Scheduling Professional (PMI-SP) — Question 21

Which of the following documents is a narrative description of products or services to be supplied by the project and has detailed requirements and pricing specified on it?

Answer options

Correct answer: C

Explanation

The correct answer is C, Statement of work (SOW), as it outlines the project deliverables, detailed requirements, and pricing. The other options, such as the Project charter and WBS, do not include the comprehensive details about products or services that the SOW provides, making them incorrect in this context.