PMI Scheduling Professional (PMI-SP) — Question 14

Which of the following processes fall under the Project Integration Management knowledge area? Each correct answer represents a complete solution. Choose all that apply.

Answer options

Correct answer: B, C, D

Explanation

The correct answers are B, C, and D as they are essential processes in Project Integration Management, which includes developing the project plan, managing changes, and executing the plan. Option A, Quality Assurance, is part of Project Quality Management and does not belong to the Integration Management processes.