A project team's risk facilitator identifies a number of risks and must prioritize them based on the organization's risk appetite levels. Which technique should be used?
Answer options
- A. PERT
- B. Stakeholder risk profile analysis
- C. Project scope statement analysis
- D. Monte Carlo technique
Correct answer: B
Explanation
The correct answer is B, as stakeholder risk profile analysis allows for assessing and prioritizing risks based on the organization's risk appetite. The other options, such as PERT and Monte Carlo technique, are useful for estimating project timelines and analyzing uncertainties but do not specifically focus on aligning risks with organizational risk tolerance.