PMI Risk Management Professional (PMI-RMP) — Question 9
A project in the execution phase at the customer's site has an issue concerning new parts that do not fit properly into a machine. The site project manager cannot find this high probability risk in the risk register.
What action should the site project manager take?
Answer options
- A. Variance analysis
- B. Workaround
- C. Risk assessment
- D. Risk audit
Correct answer: B
Explanation
The correct answer is B, as a workaround is a temporary solution to address an immediate problem when a risk is not documented. Options A, C, and D involve analyzing or assessing risks rather than providing a direct solution to an existing issue.