PMI Risk Management Professional (PMI-RMP) — Question 88

A project's risk manager successfully implements the risk management plan and the risk register. Furthermore, the risk analysis and the risk response planning are finalized. All results have been documented, and the project management plan and other project documents have been updated accordingly.
What should the risk manager do next?

Answer options

Correct answer: D

Explanation

The correct answer is D because continuous risk re-evaluation is essential for adapting to new risks and ensuring the effectiveness of risk management throughout the project. Options A, B, and C, while important, do not address the ongoing need for risk monitoring and adjustment that is critical for project success.