PMI Risk Management Professional (PMI-RMP) — Question 85
The risk manager for a construction project graphically groups project risks by the subsets of economic risk, social risk, and technical risk. Where has this information been captured?
Answer options
- A. Risk breakdown structure
- B. Risk management plan
- C. Risk register
- D. Risk control plan
Correct answer: A
Explanation
The correct answer is A, as the risk breakdown structure is specifically used to categorize and display risks in a hierarchical format. Options B, C, and D do not serve the purpose of visually grouping risks; the risk management plan outlines strategies, the risk register logs identified risks, and the risk control plan focuses on managing risks rather than categorizing them.