PMI Risk Management Professional (PMI-RMP) — Question 85

The risk manager for a construction project graphically groups project risks by the subsets of economic risk, social risk, and technical risk. Where has this information been captured?

Answer options

Correct answer: A

Explanation

The correct answer is A, as the risk breakdown structure is specifically used to categorize and display risks in a hierarchical format. Options B, C, and D do not serve the purpose of visually grouping risks; the risk management plan outlines strategies, the risk register logs identified risks, and the risk control plan focuses on managing risks rather than categorizing them.