PMI Risk Management Professional (PMI-RMP) — Question 83

During a weekly project review meeting, a stakeholder identifies some new risks. When creating risk responses for these newly identified risks, what should the project team do to discover trends and more efficiently manage the responses?

Answer options

Correct answer: A

Explanation

Classifying the risk impacts based on their severity helps the project team prioritize which risks require immediate attention and action, allowing for more effective management of responses. While listing workaround solutions, identifying risk owners, and determining root causes are valuable steps, they do not directly aid in recognizing trends for the purpose of response management.