PMI Risk Management Professional (PMI-RMP) — Question 81

A project team is conducting initial risk planning. What other risk-related task should the project manager perform?

Answer options

Correct answer: A

Explanation

Identifying the risk threshold is essential as it defines the level of risk that the project can tolerate, which helps in making informed decisions. The other options, such as determining risk register headings, scoring risks, and prioritizing risks, are important tasks but typically follow after the risk threshold has been established.