Several key stakeholders approach the project manager with concerns. The stakeholders have received feedback from local businesses that have reported a reduction in customers because of construction activities at the worksite, and they plan to submit a claim to the municipality to fine the project manager’s company.

How should the project manager address this concern?

Answer options

Correct answer: B

Explanation

The correct answer is B, as it emphasizes evaluating the risks associated with the situation and updating the issue log to reflect stakeholder concerns. Adjusting construction hours (A) may not fully address the underlying issue, while updating risks (C) without assessment isn't proactive. Discussing with local business owners (D) could be helpful but doesn't systematically manage the risk.