PMI Risk Management Professional (PMI-RMP) — Question 68
An organization that spans across different countries undergoes a digital transformation project. The project manager has assigned a risk management team leader who is a risk management certified candidate in their domain.
What should the risk management team leader do in the early stages of the project?
Answer options
- A. Plan a solid risk response plan and secure the necessary funding.
- B. Conduct a qualitative risk analysis to prioritize potential risks.
- C. Educate stakeholders on best practices to perform risk management.
- D. Benchmark to an organization which has executed a similar project.
Correct answer: C
Explanation
The correct answer is C because educating stakeholders on best practices establishes a foundation for effective risk management throughout the project. Planning a risk response plan (A), conducting qualitative analysis (B), and benchmarking with other organizations (D) are important but should follow after stakeholders are informed and engaged.