PMI Risk Management Professional (PMI-RMP) — Question 68

An organization that spans across different countries undergoes a digital transformation project. The project manager has assigned a risk management team leader who is a risk management certified candidate in their domain.

What should the risk management team leader do in the early stages of the project?

Answer options

Correct answer: C

Explanation

The correct answer is C because educating stakeholders on best practices establishes a foundation for effective risk management throughout the project. Planning a risk response plan (A), conducting qualitative analysis (B), and benchmarking with other organizations (D) are important but should follow after stakeholders are informed and engaged.