PMI Risk Management Professional (PMI-RMP) — Question 66
An IT project is 40% complete. During the initial analysis, risks A and B were identified for the project. Risk A has a probability of 0.6 and an impact of US$50,000. Risk B has a probability of 0.7 and an impact of US$60,000. After implementing the planned risk response for risk B, the probability of risk B has been reduced to 0.3.
What is the current project risk exposure?
Answer options
- A. US$30,000
- B. US$72,000
- C. US$48,000
- D. US$18,000
Correct answer: C
Explanation
To calculate the current project risk exposure, we need to assess the expected monetary value (EMV) of each risk. Risk A's EMV is calculated as 0.6 * US$50,000 = US$30,000. For risk B, after the response, the EMV is 0.3 * US$60,000 = US$18,000. Thus, the total risk exposure is US$30,000 + US$18,000 = US$48,000, making option C the correct answer, while the other options do not accurately reflect the calculations.