PMI Risk Management Professional (PMI-RMP) — Question 64
The project team is updating the risk register with the minimum acceptable level of exposure and impact for each risk. The team also wants to determine if they have reached the maximum level of exposure before they escalate the risk.
What should the team perform in this scenario?
Answer options
- A. Quantitative risk analysis
- B. Risk urgency assessment
- C. Monitor and control risks
- D. Risk response planning
Correct answer: A
Explanation
The correct answer is A, Quantitative risk analysis, as it involves measuring the probability and impact of risks to determine acceptable exposure levels. The other options do not focus on quantifying risks; B relates to urgency, C deals with ongoing risk management, and D is about planning responses rather than analyzing exposure levels.