PMI Risk Management Professional (PMI-RMP) — Question 49

A home solar panel project has many internal and external stakeholders including households, businesses, community groups, electric utility companies, local government officials, landlords, and investors. What should the project manager do when engaging stakeholders?

Answer options

Correct answer: D

Explanation

The correct answer is D because considering stakeholders' positions and opinions is crucial for the project's success and helps in aligning the project with their expectations. Option A is incorrect as not all stakeholders may need to be involved in governance, while B is wrong since ignoring risks can lead to project failure. Option C, although important, does not specifically address the need to consider stakeholders' perspectives.