PMI Risk Management Professional (PMI-RMP) — Question 46
The project manager requests a method to analyze risk data in a simple format. Which of the following formats should the risk manager suggest for preliminary review of the data?
Answer options
- A. Monte Carlo analysis
- B. Fishbone diagram
- C. Latin Hypercube analysis
- D. Data tables
Correct answer: D
Explanation
Data tables provide a clear and organized way to present risk data, making it easy for preliminary review. The other options, such as Monte Carlo analysis and Latin Hypercube analysis, are more complex statistical methods that may not be suitable for initial assessments, while Fishbone diagrams are better suited for root cause analysis rather than risk data review.