PMI Risk Management Professional (PMI-RMP) — Question 41

What quantitative tools and techniques are used to perform risk analysis in order to support stakeholder decision making for the project?

Answer options

Correct answer: B

Explanation

Sensitivity analysis is the right choice as it evaluates how different values of an independent variable will impact a particular dependent variable under a given set of assumptions. The other options, while relevant to risk management, are not primarily quantitative tools; for example, interviewing is a qualitative technique, and risk probability and impact assessment and the probability and impact matrix are more about categorizing and prioritizing risks rather than performing quantitative analysis.