PMI Risk Management Professional (PMI-RMP) — Question 39
As part of identifying the risk appetite of project stakeholders, the project manager must first identify the stakeholders. Which of the following inputs are used to identify project stakeholders?
Answer options
- A. Project charter, management reserve, enterprise environmental factors, and organizational process assets
- B. Project management plan, human resource plan, enterprise environmental factors, and organizational process assets
- C. Project charter, bid documents, enterprise environmental factors, and organizational process assets
- D. Project charter, communications management plan, enterprise environmental factors, and organizational process assets
Correct answer: D
Explanation
The correct answer is D because the project charter and communications management plan are essential for identifying stakeholders. Options A, B, and C include components that do not specifically focus on stakeholder identification or lack the necessary communications management plan.