PMI Risk Management Professional (PMI-RMP) — Question 33
The risk manager for a data center infrastructure project performs a risk audit. Which of the following represents the primary goals of the audit?
Answer options
- A. Assess performance of project team members and make required changes.
- B. Document new risks identified and take the appropriate actions.
- C. Assess responsibilities of risks that have occurred and take the appropriate actions.
- D. Document what went well and not so well with the risk management process, and recommend actions to improve.
Correct answer: D
Explanation
The correct answer, D, focuses on reviewing the risk management process to identify what strategies worked or failed, thereby enabling enhancements. Option A is incorrect because it centers on team performance rather than the risk management process itself. Option B is not correct as it emphasizes documenting new risks rather than evaluating the overall risk management efforts. Option C misinterprets the audit's goal, which is not just about responsibilities for risks but a broader assessment of the process.