PMI Risk Management Professional (PMI-RMP) — Question 33

The risk manager for a data center infrastructure project performs a risk audit. Which of the following represents the primary goals of the audit?

Answer options

Correct answer: D

Explanation

The correct answer, D, focuses on reviewing the risk management process to identify what strategies worked or failed, thereby enabling enhancements. Option A is incorrect because it centers on team performance rather than the risk management process itself. Option B is not correct as it emphasizes documenting new risks rather than evaluating the overall risk management efforts. Option C misinterprets the audit's goal, which is not just about responsibilities for risks but a broader assessment of the process.