Critical deliverables are delayed, because a key subject matter expert (SME) does not have enough time to allocate to the tasks. How could the situation be improved for the future?
Answer options
- A. Cross train others to reduce the SME workload.
- B. Introduce scope reductions to limit the reliance on SMEs.
- C. Replace the SME with resources, who are responsible for receiving output from the SME on their deliverables.
- D. Extend the project schedule timeline to accommodate availability of the SME.
Correct answer: A
Explanation
The correct answer, A, suggests cross-training others, which can lessen the dependency on one SME and distribute the workload more evenly. Options B and D do not address the root cause of the issue and may lead to further delays or reduced project quality. Option C removes the SME but does not ensure that the new resources have the necessary expertise, which could lead to misunderstandings and errors in deliverables.