PMI Risk Management Professional (PMI-RMP) — Question 29

A project manager is creating a risk management plan. The project sponsor does not see the need for additional risk management, believing that the only risks to the project are financial risks.
What procedure could the project manager use to identify other potential topics such as technical, quality, performance, project management, internal and external risks?

Answer options

Correct answer: D

Explanation

The correct answer is D because using existing prompt lists and a risk breakdown structure helps in systematically identifying various types of risks beyond just financial ones. Options A, B, and C focus on specific analysis techniques or factors that may not comprehensively cover all potential risks relevant to the project.