PMI Risk Management Professional (PMI-RMP) — Question 204
The expected monetary value of a project is above USS1 million. The risk manager is concerned about this situation, and decides to review the related plans and processes to evaluate the degree of variation from the baseline. Next, the risk manager needs to document the results of such an analysis.
What is the best document for the project manager to reference to find out where the results of such an analysis should be documented?
Answer options
- A. Communications management plan
- B. Issues log
- C. Risk management plan
- D. Lessons learned
Correct answer: A
Explanation
The Communications management plan outlines how information will be documented and shared throughout the project, making it the appropriate reference for the risk manager's analysis results. The Issues log is used for tracking problems, the Risk management plan focuses on risk identification and strategies, and the Lessons learned document captures knowledge from past experiences, but does not specifically address documentation of analysis results.