PMI Risk Management Professional (PMI-RMP) — Question 194

During the execution of a multi-million dollar project, the project manager learns of the theft of important installation materials at one of the most time-critical sites.
The project manager contacts the risk manager to discuss further steps, based on the risk register and the defined risk strategy for the risk of theft. However, the risk manager clarifies that the risk of theft was not identified in the risk management process.
What should the project manager do next?

Answer options

Correct answer: C

Explanation

The correct answer is C because transferring the risk to an insurance company helps mitigate the financial impact of the theft, while capturing the experience in lessons learned aids in future project planning. Options A and D place undue responsibility on the risk manager without addressing the financial risk effectively. Option B does not address the theft issue directly and only focuses on communicating delays.