PMI Risk Management Professional (PMI-RMP) — Question 191
As part of standard procedure to monitor and control a project, a risk manager should constantly update the risk register. The risk register updates should include information on risk reassessment, risk audits, and periodic risk reviews.
What additional information should the risk manager prioritize in the risk register updates?
Answer options
- A. Actual outcomes of the project's risks and risk responses
- B. Actual outcomes and performance of risk management strategies
- C. Actual costs and schedule delays of risk events
- D. Actual cost impact of risk events
Correct answer: B
Explanation
The correct answer, B, is crucial because it focuses on the effectiveness of risk management strategies, which informs future planning and risk assessment. Options A, C, and D provide valuable information but do not directly evaluate the performance of the risk management strategies themselves, making them less prioritized in the context of strategic updates.