PMI Risk Management Professional (PMI-RMP) — Question 186

A risk manager is part of a team overseeing the implementation of a new customer relationship management system for a retail organization. The client has provided an initial timeline for implementation that includes tight deadlines but lacks details about resource allocation.

What should the risk manager do?

Answer options

Correct answer: C

Explanation

The correct answer, C, emphasizes the importance of collaboration with stakeholders to ensure the right resources are available when needed, which is crucial for meeting project milestones. Option A is incorrect as it ignores the necessity of resource planning, which may jeopardize the project. Option B is flawed because delaying resource discussions can lead to issues during execution. Option D is risky, as it leaves important resource decisions to chance, potentially impacting project success.