PMI Risk Management Professional (PMI-RMP) — Question 181

A risk manager is part of a software development project and has just completed the initial risk identification process. The team has compiled a lengthy list of risks, but stakeholders have emphasized the need to focus only on the most significant risks due to limited resources.

What should the risk manager do?

Answer options

Correct answer: C

Explanation

The correct answer is C because analyzing risks based on probability and impact allows the risk manager to effectively prioritize the most significant risks, ensuring that resources are allocated appropriately. Option A is incorrect as it disregards further analysis of low-priority risks, while B oversimplifies the process by ignoring significant risks that may have lower probabilities. Option D relies too much on subjective perceptions, which may not accurately reflect the actual severity of the risks.