A complex project that had hundreds of risks is almost done. The project manager is closing the risks as part of the closing process. One team member mentions that there are important documents to be updated.

Which document will need to be updated?

Answer options

Correct answer: D

Explanation

The Risk Register needs to be updated to reflect the closure of risks as the project comes to an end. The Lessons learned document captures insights from the project but does not directly reflect current risks. The Issue log tracks problems encountered during the project, and the Contingency register holds planned responses to risks but is not the primary document for closing risks.