PMI Risk Management Professional (PMI-RMP) — Question 171
What would be the next step after determining the agreed-upon risk response for a specific risk?
Answer options
- A. Add the risk response to the project management plan and document the predicted exposure.
- B. Evaluate the project related implications and update the risk response to the project management plan if needed.
- C. Document the predicted exposure.
- D. Communicate to stakeholders.
Correct answer: D
Explanation
The correct answer is D, as communicating to stakeholders is essential to ensure they are aware of the risk response and its implications. While options A, B, and C involve important documentation and evaluation processes, they do not prioritize stakeholder communication, which is crucial for project transparency and alignment.