PMI Risk Management Professional (PMI-RMP) — Question 168
What items should be included in a complex project's risk management plan?
Answer options
- A. Risk management methodology, scope statement, and thresholds and corresponding definitions
- B. Risk management methodology, risk management organization, and thresholds and corresponding definitions
- C. Risk management organization, templates, and milestone plan
- D. Risk management organization, risk communication plan, and milestone plan
Correct answer: B
Explanation
The correct answer is B because a comprehensive risk management plan requires a defined methodology, an organizational structure for managing risks, and specific thresholds with definitions to assess risk levels effectively. Options A, C, and D include components that are either incomplete or less relevant for a robust risk management strategy.