PMI Risk Management Professional (PMI-RMP) — Question 165

During the risk Monitor and Control Project Work process, the scope, schedule, and cost begin to increase. What outputs should be updated and/or created?

Answer options

Correct answer: B

Explanation

The correct answer is B because change requests are necessary to address the variations in scope, schedule, and cost, which must then be reflected in the project management plan and project documents. The other options include items that are not typically updated or created in response to these changes, such as the human resource plan in option A, or the cost plan in option C.