PMI Risk Management Professional (PMI-RMP) — Question 160
Some engineers are completing an activity that will alert the project team if there is a risk of requiring additional effort to complete the project. What should the risk manager do in case the trigger arises?
Answer options
- A. Request a reserves increase.
- B. Update the risk response plan.
- C. Activate the contingency plan.
- D. Add the alert to the risk register.
Correct answer: B
Explanation
The correct answer is B, as updating the risk response plan allows the risk manager to adjust strategies based on the new information. Option A is incorrect because requesting a reserves increase is not a proactive risk management step. Option C, activating the contingency plan, would only be necessary if the risk has materialized, not just when a trigger is identified. Option D is also incorrect since adding the alert to the risk register is a documentation step, not a strategic response.