PMI Risk Management Professional (PMI-RMP) — Question 152
The trigger for a highly categorized threat has occurred. The risk has set a response plan.
Who is responsible for developing responses to risk and monitoring the implementation status of the risk response?
Answer options
- A. Product Manager
- B. Risk Owner
- C. Project Manager
- D. Risk Action Owner
Correct answer: D
Explanation
The Risk Action Owner is specifically designated to formulate responses to risks and track the execution of those responses. The Product Manager, Risk Owner, and Project Manager may have roles in risk management, but they do not directly handle the development and monitoring of risk response plans.