PMI Risk Management Professional (PMI-RMP) — Question 150
The risk manager also serves as a facilitator for a project and realizes the project team members have biases impacting how they perceive risks. What analysis is currently being used?
Answer options
- A. Qualitative risk analysis
- B. Force field analysis
- C. Stakeholder analysis
- D. Quantitative risk analysis
Correct answer: C
Explanation
The correct answer is C, Stakeholder analysis, as it focuses on understanding the perspectives and biases of those involved in the project. The other options do not specifically address the biases of project team members; Qualitative and Quantitative risk analyses focus on assessing risks themselves, while Force field analysis is used to understand the forces for and against a change.