PMI Risk Management Professional (PMI-RMP) — Question 150

The risk manager also serves as a facilitator for a project and realizes the project team members have biases impacting how they perceive risks. What analysis is currently being used?

Answer options

Correct answer: C

Explanation

The correct answer is C, Stakeholder analysis, as it focuses on understanding the perspectives and biases of those involved in the project. The other options do not specifically address the biases of project team members; Qualitative and Quantitative risk analyses focus on assessing risks themselves, while Force field analysis is used to understand the forces for and against a change.