PMI Risk Management Professional (PMI-RMP) — Question 145

A project is at the final development stage. The test lead informs the risk manager that a key feature may not be testable due to changes in the environment. What should the risk manager do?

Answer options

Correct answer: B

Explanation

The correct answer is B because developing acceptance criteria is essential to ensure that the feature can be evaluated properly despite the changes. Option A is less effective as simply reviewing the feature does not address the underlying issue. Option C may escalate the problem but fails to provide a direct solution, and option D does not resolve the issue of the feature's testability.