PMI Risk Management Professional (PMI-RMP) — Question 145
A project is at the final development stage. The test lead informs the risk manager that a key feature may not be testable due to changes in the environment. What should the risk manager do?
Answer options
- A. Review the feature with the project team.
- B. Ask the architect to develop acceptance criteria.
- C. Escalate the issue to the project board.
- D. Confirm the risk triggers are still valid.
Correct answer: B
Explanation
The correct answer is B because developing acceptance criteria is essential to ensure that the feature can be evaluated properly despite the changes. Option A is less effective as simply reviewing the feature does not address the underlying issue. Option C may escalate the problem but fails to provide a direct solution, and option D does not resolve the issue of the feature's testability.