PMI Risk Management Professional (PMI-RMP) — Question 143
While planning for project execution phase stakeholders are making decisions on how to respond to known and new risks. What artifact should the stakeholders prepare?
Answer options
- A. Assumption log
- B. Risk-adjusted back log
- C. Issue log
- D. Change log
Correct answer: D
Explanation
The correct answer is D, the Change log, as it is essential for tracking modifications made in response to risks and issues throughout the project. The Assumption log (A) captures assumptions made, the Risk-adjusted backlog (B) is not a standard term, and the Issue log (C) focuses on current problems rather than planned responses to risks.