PMI Risk Management Professional (PMI-RMP) — Question 134

A new risk manager has been hired on a project and meets with the project director. The project director supplies the project’s risk register and asks the risk manager for an analysis of its effectiveness.

What two actions should the risk manager do next? (Choose two.)

Answer options

Correct answer: C, D

Explanation

The correct actions are C and D. Action C is crucial because having an agenda and supporting documents ensures that the risk meeting is structured and informative. Action D is important as identifying the risk's origin, triggering event, and ownership is fundamental for effective risk management, while actions A, B, and E don't directly address the immediate evaluation of the risk register's effectiveness.