PMI Risk Management Professional (PMI-RMP) — Question 11

Within the organizational process assets, where would the project manager find risk response effectiveness from past projects?

Answer options

Correct answer: C

Explanation

The correct answer is C because risk audits provide insights into the effectiveness of risk responses utilized in past projects, and lessons learned offer documented experiences that can be referenced. The other options do not specifically focus on risk response effectiveness as much as option C does.