PMI Risk Management Professional (PMI-RMP) — Question 109
The project manager needs to create a risk management plan for a high risk project, but the company's senior management does not see value in spending time documenting major risks instead of leading the project. What is the most appropriate action for the project manager to take first?
Answer options
- A. Develop a risk register and present it to the senior management.
- B. Hire a risk consultant to identify the major risks.
- C. Develop a risk management plan and present it to the sponsor.
- D. Document all identified risks.
Correct answer: A
Explanation
The correct answer is A because creating a risk register provides a structured overview of risks that can help senior management understand the importance of risk management. The other options either involve additional costs (B), focus on a deliverable that may not address the immediate concern of gaining management's buy-in (C), or do not effectively communicate the risks to decision-makers (D).