PMI Professional in Business Analysis (PMI-PBA) — Question 95
An organization is in the process of replacing its current system. The business analyst is charged with ensuring that all current connections to other systems remain functional after the upgrade.
What analysis should the business analyst conduct to facilitate a successful migration?
Answer options
- A. Systems
- B. Interface
- C. Document
- D. User interface
Correct answer: A
Explanation
The correct answer is A, Systems analysis, as it focuses on understanding the entire system architecture and its connections, which is crucial for maintaining functionality during migration. Option B, Interface, specifically pertains to connections between systems, but does not encompass the broader system aspects necessary for a successful upgrade. Options C and D, Document and User interface respectively, are not directly related to ensuring system connections remain operational.