PMI Professional in Business Analysis (PMI-PBA) — Question 69
The document that defines the process for managing requirements revisions is the:
Answer options
- A. project management plan.
- B. communications management plan.
- C. scope management plan.
- D. change management plan.
Correct answer: D
Explanation
The change management plan is specifically designed to outline how changes to project requirements are handled, making it the correct choice. The project management plan is broader and does not focus solely on requirements, while the communications and scope management plans address different aspects of project management.