PMI Professional in Business Analysis (PMI-PBA) — Question 52
The project sponsor needs to know which requirements will be implemented. Which of the following would be the most valuable for a business analyst to provide?
Answer options
- A. Requirements baseline document
- B. Requirements management plan
- C. Requirements impact analysis
- D. Requirements traceability matrix
Correct answer: A
Explanation
The Requirements baseline document is crucial as it outlines the agreed-upon requirements for the project, providing clarity on what will be implemented. The Requirements management plan focuses on how requirements will be managed, while the Requirements impact analysis assesses changes and their effects. The Requirements traceability matrix connects requirements to their origins, but does not specify what will be implemented.