PMI Professional in Business Analysis (PMI-PBA) — Question 44
Testing on a project has been completed. In order to proceed with deployment, a decision is needed.
Who should the business analyst contact to review the testing results and get approval to proceed with deployment?
Answer options
- A. The tester identified in the testing strategy
- B. The project manager identified in the project charter.
- C. The project sponsor identified in the scope document.
- D. The person identified in the RACI matrix.
Correct answer: D
Explanation
The correct answer is D because the RACI matrix outlines roles and responsibilities, including who is accountable for approvals. The tester (A) is responsible for testing, the project manager (B) oversees project execution, and the project sponsor (C) provides support but does not directly handle the approval process.