PMI Professional in Business Analysis (PMI-PBA) — Question 22

In the middle of a project, a new requirement was added to the scope. The business analyst must determine if any impacts, dependencies, or risks are associated with the addition to the scope.
What task should the business analyst perform in order to identify these impacts?

Answer options

Correct answer: C

Explanation

The correct answer is C, as managing the solution scope allows the business analyst to evaluate how the new requirement affects the overall project. The other options do not directly address the evaluation of impacts related to changes in scope.